Client Name      Transfer of Safety Related Production Line
Brief Description      Provide client with feasibility study on commodity groups most suitable for transfer into low-cost supply chain.
Date      2006
Location      UK
Type     
Size     
Value     
Overview     

Project Scope: 

  • Identify strategic source for production of two product lines (Fuel and Hydraulic tank)s for a leading OEM within the Yellow goods market, by evaluating the technical and commercial risks to find most suitable partnership
  • Develop contract terms between client and supplier ensuring the risk is mitigated
  • Assist in developing a technical transition document capturing product tribal knowledge
  • Translation of technical specifications and standards from the clients systems into the suppliers ensuring the exact requirements of the client are documented and understood by the supplier.
  • Comprehensive Project Management and planning service; including resource management from clients internal activities through to the suppliers actions.
    • Use of Gantt Charts
    • Critical Path evaluation
    • Risk Management
    • Technical Translation Service
  • Post transfer support and order logistics management

Activity:

  • Central and Easter European supply chains evaluated for our client from over 150 potential suppliers.
  • Feasibility report provided identifying potential partners including:
    • Anticipated recurring cost
    • NRC
    • Logistics
    • Packaging
    • Project timing
  • Full RFQ process managed by RCL providing proposed solution
  • 2 week sabbatical from RCL engineer into clients facility to document “tribal” knowledge and translate inspection standards and procedures as necessary
  • “Lean Manufacturing” development of clients existing facility in preparation for transfer to reduce direct labour costs for both client and supplier (eliminate Non-Value-Added)
  • Project management with timing and schedule development controlling:
    • Communication
    • Resource
    • Layout developmen
    • Risk
  • Post transfer support: 1 day per week RCL visit to supplier to coordinate order control, logistics and quality improvement initiatives.
    • Evaluate opportunities to improve productivity

Result:

Quality:

  • Target Defect ratio achieved by supply chain
  • 100% pressure test of tanks within suppliers facility


Cost:

  • Forecasted level of direct cost reduction achieved
  • Total acquisition cost reduced by client
    • JIT supply
    • 3 day dock-to-dock
    • Improved return on capital employed

Delivery:

  • Project SOP date achieved
  • Bi-weekly “milk-run” for supplier deliveries developed
  • Direct-line feed to minimise non-value added storage area

 